CWL ROAD CONSTRUCTION UPDATE!

Posted on Jun 5, 2017

The road construction has been delayed. 

Phase 1 (Constitution) is anticipated to start on Tuesday, June 6th.  The road will be closed at 7:30 AM.

Phase 2 (Marquette) is anticipated to start on Tuesday, June 6th, after Phase 1 has been completed.

Phase 3 (Redman from Marquette to Quincy) road work will be started when Phase 2 is completed.  It is anticipated that this could start Tuesday, June 6th in the afternoon or by 7:30 AM on Wednesday.

Phase 4 (Constitution) – It is anticipated that this road work will be completed on Wednesday.

Phase 5 (Redman (Quincy to cul de sac) and Drury) – It is anticipated that this road work will be completed on Wednesday, after Phase 4 has been completed.